Project Schedule Assignment
February 18th, 2020
Consider the project schedule shown in the table below. Activity Predecessor(s) Duration 1 EF 1 3 LS 0 Slack 0 Α. 0 C Α. Α BD 9 E B, C 4 1 7 1 4 1 7 F с 7 G E, F 7 11 7 T What is the slack time for activity C? O A. 3 OB. O OC. 2 OD. 1. Get Accounting homework help today